The Department of State Development, Infrastructure, Local Government and Planning is changing to the Department of State Development and Infrastructure. Work is underway to update this website. Read more about the new Ministerial portfolios. Access Planning and Local Government content as changes are being progressed.

Skip to content

Project changes

Since the publication on the Coordinator-General's report on the EIS, New Acland Coal Pty Ltd has applied for the following changes to the New Acland Coal Mine Stage 3 project.

Project  change application 4 – amendment to stated conditions following Land Court (2021) proceedings

DateActivity
26 May 2022 Coordinator-General’s report on project change released (PDF icon 4.4 MB), approving the change.
30 March 2022 Proponent’s change application submitted (PDF icon 31 MB).

Project change application 3 – amendment to stated conditions B3 and H40

DateActivity
29 September 2020 Coordinator-General’s report on project change released (PDF icon 5.8 MB), approving the change.
8 May 2019 Proponent’s change application submitted (PDF icon 522 KB).

Project change application 2 – Train load-out facility

DateActivity
17 September 2020 Coordinator-General’s report on project change released (PDF icon 1.1 MB), approving the change.
22 June 2019 to 21 July 2019 Public consultation on project change application (PDF icon 1.1 MB).
24 May 2019 Proponent’s change application submitted.

Project change application 1 – Noise

DateActivity
12 February 2019 Coordinator-General's report on project change released (PDF icon 336 KB), approving the change.
3 December 2018 Proponent’s change application submitted (PDF icon 2.9 MB).

Read more about project changes.