Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Cross River Rail project.

Project change application 6 – temporary change of certain work hours 2020

Date Activity
7 May 2020

Coordinator-General's report on project change (PDF icon462 KB) released, approving the change.

7 May 2020

The Coordinator-General decided not to publicly notify the proponent’s change application.

29 April 2020

Proponent’s change application submitted (PDF icon 215 KB).

Project change application 5– Condition change (hours of work) 2019

Date Activity
4 October 2019

Coordinator-General's report on project change (PDF icon1.6 MB) released, approving the change.

3 October 2019

The Coordinator-General decided not to publicly notify the proponent’s change application.

23 September 2019

Proponent’s change application submitted (PDF icon 899 KB).

Project change application 4 – Whole of project refinements 2019

Date Activity
26 June 2019 Coordinator-General’s report on project change (2 MB) released, approving the change
21 June 2019

Proponent submitted additional information:

20 May 2019 to 14 June 2019

Public consultation of project change application.

Volume 1 - Request for project change 4 application (40 MB)

Volume 2 - Design drawings:

Drawing index and locality plans

General arrangement drawings:

Long section drawings (3 MB)

Station drawings (7 MB)

Tunnel and portal drawings (23 MB)

Property impact drawings:

General construction site plan drawings:

Volume 3 - Technical reports (86 MB)

1 May 2019 Proponent's change application submitted.

Project change application 3 – Roma Street demolition works

Date Activity
14 March 2019

Coordinator-General's report on project change (PDF icon 1.6 MB) released, approving the change.

4 March 2019

Proponent submitted revised information:

Roma Street demolition works updated traffic assessment technical note (PDF icon 15 MB)

1 December 2018 to 21 December 2018

Public consultation of project change application.

19 November 2018

Proponent's change application submitted.

Project change application 2 – Temporary Roma Street Coach Terminal

Date Activity
31 August 2018 Coordinator-General's report on project change (PDF icon 824 KB) released, approving the change.
23 August 2018

Proponent submitted revised information:

3 August 2018

Proponent submitted revised information:

17 July 2018

The Coordinator-General decided not to publicly notify the proponent's change application.

28 June 2018

Proponent's change application submitted:

Project change application 1 – Whole of project

Date Activity
9 June 2017Coordinator-General's report on project change (PDF icon 1.5 MB) released, approving the change.
3 April 2017 to 21 April 2017

Extension to public consultation on project change application.

Amended Volume 3 – Cross River Rail design diagrams – All documents not listed here that were subject to consultation over the period 25 February 2017 and 27 March 2017 remain unaltered:

31 March 2017 Coordinator-General decided to extend the public consultation period.
25 February 2017 to
27 March 2017

Public consultation on project change application.

Volume 1 – Request for project change (PDF icon 34.4 MB)

Volume 2 – Draft outline environmental management plan (PDF icon 3 MB)

Volume 3 – Cross River Rail design drawings – sections

Volume 4 – Technical reports (PDF icon 28.6 MB)

5 December 2016 Proponent's project change application submitted.

Read more about project changes.